Bond Information

In 2001, North Kitsap voters approved a $60 million bond for building upgrades, renovations and construction of Kingston High School. The district was able to qualify for an additional $40 million through state matching funds and a Public Facilities District grant. Due to a favorable construction climate, an advantageous bond market, and the additional public funds more projects were completed than initially outlined in the bond description. The district had approximately $410K left to fund additional projects and the board approved a list of additional projects. View the approved list of additional projects.
 

Projects:  

North Kitsap Community Pool/Auditorium - Upgrades

Completed: September 2002

Construction Costs: $4,173,310

 

North Kitsap High School Gym/H Building - Renovation

Completed: August 2004

Construction Costs: $8,783,860

 

Hilder-Pearson Elementary School - Renovation

Completed: June  2005

Construction Costs: $5,036,856

 

Poulsbo Elementary School - Renovation

Completed: June 2005

Construction Costs: $5,912,698

 

Suquamish Elementary School - Renovation

Completed: September 2005

Construction Costs: $4,867,509

 

Poulsbo Middle School Bldg. 1 - Renovation

Completed: March 2007

Construction Costs: $7,639,206

 

Wolfle Elementary School -  New Roof

Completed: February 2008

Construction Costs: $414,376

 

Kingston High School - New Construction (includes field lighting, track shed and tennis courts)

Completed: June 2008

Construction Costs: $39,034,998

 

Spectrum Community School – Renovation

Completed: August 2008

Construction Costs: $455,335

 

North Kitsap High School Phase II - Addition/Renovation

Completed July 2009

Construction Costs: $21,503,949

 

North Kitsap High School Track Resurface (Not included in initial bond description.)

Completed: Ongoing       

Construction Costs: $102,243

 

Poulsbo Elementary School Security Upgrades (Not include in initial bond description.)

Completed: Ongoing

Construction Costs: $14,534

 

Total spent and committed to date:                            

$97,938,874.00